Indian Queens private wire: 33kV cable route
Civils and cable installation for Novus Power's 7.8km 33kV private wire, from the Tregonning Solar Farm to National Grid's Indian Queens substation in Cornwall.
The project
Ground Utilities is delivering the civils and cable installation for Novus Power's 7.8km 33kV private wire, which runs from the Tregonning Solar Farm to National Grid's Indian Queens substation in Cornwall. The route crosses farmland and Cornish hedges, passes through the village of Fraddon and follows the B3279. In all, about 46km of single-core 33kV cable is being installed. The HDD crossings are being carried out separately by the client.
Scope of works
- CDM set-up, traffic management and highway permits, including council liaison and the Section 50 licence
- Surveys, trial holes and HSG47 hand digging at 22 areas of concern
- 7.3km of open-cut trench: 3.3km in farmland and 4km in the highway
- About 46km of 33kV cable: two circuits of 3 x 630/800mm² aluminium XLPE, laid in trefoil
- 19 joint bays, fibre ducts and nine fibre chambers
- Full reinstatement of the highway, hedges and farmland
Challenges overcome
- Material delays: cable drums and ducts arrived late, so the works were re-sequenced to keep progressing.
- Winter working: trackway, ground protection and dewatering on waterlogged farmland.
- Fraddon village: 16 gas services in around 300m of narrow road, all hand dug.
- Community liaison: letter drops, access kept open and 10 bus stop suspensions.
- National Grid substation: work under National Grid safety rules and permit to work.
- Deep crossings: around 2.9m deep, beneath a high-pressure gas main and a trunk main.
Project facts
- Location
- Cornwall
- Type
- Cable Installation
- Started
- June 2026
- Due to finish
- February 2027
- Services
- Multi utility services
Related projects
All projects
HV cable installations
Two 33kV circuits and fibre over about 25 km between a DNO substation and a new client substation, fully ducted, with 45 joint bays. May 2018 to September 2019.
View project
5 x 33kV with fibre optic
Five 33kV circuits with fibre for a new data centre and a generation site: about 53,000 metres of cable in a fully ducted route along main roads. August 2018 to April...
View project
Irrigation main installation
A high-pressure irrigation main with thrust blocks, two road crossings, reinstatement and full system testing. February to March 2021.
View projectPlanning a scheme?
Tell us the route, the voltage and the programme, and we will come back to you.