HV cable installations
Two 33kV circuits and fibre over about 25 km between a DNO substation and a new client substation, fully ducted, with 45 joint bays. May 2018 to September 2019.
The project
Ground Utilities carried out the excavation, reinstatement and HV and fibre cable installation for two 33kV circuits between a DNO substation and a new client substation in Cambridgeshire. The route is about 25 km long and fully ducted. It runs through towns and villages, in the highway, footpath and verge.
Scope of works
- About 25 km of fully ducted trench in highway, footpath and verge
- About 205,000 metres of 33kV and fibre cable installed
- 45 joint bays built, each fully reinstated after jointing
- Crossings of bridges, culverts and watercourses, and of the existing services along the route
The work was completed within the agreed programme.
See our HV cable installation service, 240V to 132kV, for what a cable route involves, and the cable ducting guide.
Project facts
- Location
- Cambridgeshire
- Type
- Cable Installation
- Started
- May 2018
- Completed
- September 2019
- Services
- Multi utility services
Related projects
All projects
5 x 33kV with fibre optic
Five 33kV circuits with fibre for a new data centre and a generation site: about 53,000 metres of cable in a fully ducted route along main roads. August 2018 to April...
View project
Irrigation main installation
A high-pressure irrigation main with thrust blocks, two road crossings, reinstatement and full system testing. February to March 2021.
View project
Refurbishment of overhead line circuits
Two 33kV and two 11kV underground ducted circuits on an overhead line refurbishment: about 31,800 metres of cable and 13 joint bays. August 2020 to May 2021.
View projectPlanning a scheme?
Tell us the route, the voltage and the programme, and we will come back to you.