Wanlip STW inlet works civils
The inlet civils package at Severn Trent's Wanlip Sewage Treatment Works near Leicester, built for Kier inside the live, operational works.
The project
Wanlip Sewage Treatment Works serves the City of Leicester and the surrounding area, the second largest population served by a single works in the Severn Trent region. As part of the Wanlip STW Green Recovery project, Kier is improving river water quality through phosphorus removal and addressing growth in the catchment.
Working for Kier inside the live, operational works, Ground Utilities is delivering the inlet civils package (WF3, WF4 and WF5): the ducting, drainage, slab and foundations for the new inlet screens and screenings handling plant. Our September project update shows the slab, push walls and drainage channel as they were completed.
Scope of works
- Site preparation, setting out and temporary works design (TWD)
- 150mm Class 2 electrical ducting and draw pits from the new inlet MCC, including four road crossings
- DN100, DN150 and DN200 wash water pipework and DN150 drainage pipework, pressure tested to Severn Trent's specification
- Two 1050mm manholes and connections into the existing inlet channel
- ACO channel drainage to the main slab and the screenings push bay
- A 300mm reinforced concrete slab, and plinths for the access platforms, wash water kiosk, washpactors and backwash strainers
- A reinforced concrete push bay and walls for screenings handling
- Dewatering, waste segregation and removal of excavated material
Project facts
- Location
- Leicestershire
- Type
- Sewers & Water
- Started
- March 2026
- Due to finish
- December 2026
- Services
- Waste water, Civil construction
Related projects
All projects
Deep excavations for sewer and water service
Fifteen excavations, more than 3 metres deep at the deepest, to expose and support an existing sewer and other utilities for a diversion route. August to October 2021.
View project
Wanlip STW 11kV substation build
Services enabling and civil works for a new 11kV substation and Severn Trent's new 11kV switch room at Wanlip Sewage Treatment Works, for Kier.
View project
Irrigation main installation
A high-pressure irrigation main with thrust blocks, two road crossings, reinstatement and full system testing. February to March 2021.
View projectPlanning a scheme?
Tell us the route, the voltage and the programme, and we will come back to you.