East Cambridgeshire District Council

Burwell Solar Farm

Burwell Solar Farm will be an important source of low carbon electricity and will help meet the average annual domestic electricity requirements of up to 9,500 households.

Reeding House

Lorem ipsum dolor sit amet, dolor sit amet dolor sit amet.

Brief.

Support the UK Government to meet its decarbonisation targets to reduce net carbon emissions to zero by 2050 by constructing a 49.8 MW Solar Farm.

Project details.

Project Type
Burwell Solar Farm
Location
Burwell
Start
4th Quarter 2022
Completion
Planned August 2023
Area
Height

In August 2020 East Cambridgeshire District Council granted planning permission for Burwell Solar Farm.

The 80 hectare site located in Burwell in south east Cambridgeshire will have a generating capacity of 49.8 MW and will connect directly to the national grid substation at Burwell.

The site is in the preparation and construction stage, with the expectation that first generation will be in Q4 2022, with the solar farm becoming fully operational by March 2023.

Burwell Solar Farm will be an important source of low carbon electricity and will:

  • Meet the average annual domestic electricity requirements of up to 9,500 households
  • Support the UK Government to meet its decarbonisation targets to reduce net carbon emissions to zero by 2050