HV Cable Installations

5 x 33KV with Fibre Optic Protections

North London, a two-customer requirement of 5 x 33KV circuits with Fibre Optic Protections, in preparation for a new data centre and to export power from a Generation Site.

Reeding House

Lorem ipsum dolor sit amet, dolor sit amet dolor sit amet.

Brief.

North London, a two-customer requirement of 5 x 33KV circuits with Fibre Optic Protections, in preparation for a new data centre and to export power from a Generation Site. All circuits from the same Substation and with 0.5miles of point of connections.

Project details.

Project Type
5 x 33KV with Fibre Optic Protections
Location
London
Start
August 2018
Completion
April 2020
Area
Height

The works consisted of a fully ducted route for both clients through main arterial roads into London. To reduce trench width a double stack of ducts was required. 

The route crossed waterways, major road intersections and within Type 0 road constructions, bespoke cable lengths were also required to enable reduction of Joint Bay constructions, approximately 53,000mts of 33KV and Fibre cable were installed. 

24hr working was required to reduce programme disruption.

This project received commendations from both Haringey and Enfield councils for how well it was carried out and within timescales.

  • 53,000 Metres of 33KV & Fibre Cable Installed
  • 24 hour works
  • Works Completed within timescale
Awards